Limits on what Xcel can charge customers for Boulder Smart Grid

Submitted by Lili Francklyn on November 10, 2010 – 6:34pm

Under the settlement Xcel would be entitled to full cost recovery from 1.4 million ratepayers across Colorado – not exceeding $44.5 million.

The utility’s SmartGridCity, originally estimated at roughly $15 million – and not to be incurred by Boulder ratepayers – has seen costs rise to more than $44.5 million since its 2007 inception.

If no protests are lodged within 20 days, the PUC will adopt the recommendation and pass the cost of Xcel’s SmartGridCity onto ratepayers.  Email the PUC with protests or complaints;